HeidelbergCement AG

Convincing energy concept

After 3 years of construction, the new HeidelbergCement headquarters in Heidelberg was completed in 2020. The focus during the realization was especially on a high level of user comfort with the lowest possible energy consumption. With the use of innovative technologies, the high requirements for heating, ventilation, sanitary and cooling technology were realized. The ventilation center consists of 18 ventilation units with a capacity of 120,000 m3 /h. For this purpose, more than 10,000 m² of ventilation ducts were delivered from our own production facility, the Green Factory in Ungerhausen, and installed on site. The offices in the new headquarters are heated and cooled in a resource-saving manner with the help of district heating, geothermal energy and concrete core activation. Decentralized ventilation units were used for individual control.

Ventilation

  • 18 ventilation units: 120,000 m³/h
  • 1,034 decentralized ventilation units
  • Hygienic kitchen ventilated ceilings with integrated Capture-Jet technology: 25,000 m³/h
  • Over 10,000 m² of ventilation ducts from the Green Factory
  • 120,000 m stainless steel and steel pipes H-K-S DN 15 to 300

Heating

  • District heating transfer station with 1,100 kW
  • 3,400 m² underfloor heating
  • Heating and cooling ceilings
  • Reversible heat pumps with 750 kW
  • Reversible well system

Cooling

  • Chiller with 992 kW
  • hybrid recirculating chiller with 1,354 kW
  • Split cooling including 6 outdoor units

Fire protection

  • 500 fire dampers
  • Smoke extraction and CO2 warning system: 210,000 m³/h
  • 90,000 m of aluminum-laminated insulation
  • 2 extinguishing water supply systems (dry lines)

More information about this project in the Alois Müller storyboard
“HEIDELBERGCEMENT”

Heidelberg Cement

200922_HDC_Aussen_Detail_L3009339_12mpx-scaled

Heidelberg Cement

Lüftungszentrale im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Lüftungszentrale mit Alois Müller Mitarbeiter im neuen Headquarter der HeidelbergCement AG.

Lüftungszentrale im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Lüftungszentrale im neuen Headquarter der HeidelbergCement AG.

Lüftungszentrale im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Lüftungszentrale im neuen Headquarter der HeidelbergCement AG.

Lüftungszentrale im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Lüftungszentrale im neuen Headquarter der HeidelbergCement AG.

Lüftungszentrale im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Lüftungskanäle der Lüftungszentrale im neuen Headquarter der HeidelbergCement AG.

Lüftungsanlage auf dem Dach des neuen Headquarters der HeidelbergCement AG.

HeidelbergCement

Lüftungsanlage auf dem Dach des neuen Headquarters der HeidelbergCement AG.

Kältetechnik im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Kältetechnik im neuen Headquarter der HeidelbergCement AG.

Kältetechnik im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Kältetechnik im neuen Headquarter der HeidelbergCement AG.

Kältetechnik im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Kältetechnik im neuen Headquarter der HeidelbergCement AG.

Tiefgarage mit Lüftungskanälen im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Tiefgarage mit Lüftungskanälen im neuen Headquarter der HeidelbergCement AG.

Tiefgarage mit Lüftungskanälen im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Tiefgarage mit Lüftungskanälen im neuen Headquarter der HeidelbergCement AG.

Gebäudetechnik im neuen Headquarter der HeidelbergCement AG

HeidelbergCement

Trinkwasseranlage und Gebäudetechnik im neuen Headquarter der HeidelbergCement AG

Gebäudetechnik GROB-WERKE Mindelhei

HeidelbergCement

Gebäudetechnik im neuen Headquarter der HeidelbergCement AG.

Foyer im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Foyer im neuen Headquarter der HeidelbergCement AG.

Lüftung Magistrale im 2. OG im neuen Headquarter der HeidelbergCement AG.

HeidelbergCement

Lüftung Magistrale im 2. OG im neuen Headquarter der HeidelbergCement AG.